Construction site diary: what to record every day

A site diary is only worth keeping if it answers a question someone asks months later. Here is what to record, what an entry looks like, and where diaries usually fall down.

Written for UK contractors · Updated October 2026

Why keep a site diary

Most days, nobody looks at the diary. Then a client disputes a delay, a supplier says a delivery never arrived, or an accident leads to questions about who was on site and what they were doing. At that point the diary is the only record of what happened that was written when it happened, not reconstructed afterwards.

There is no single law that says you must keep a site diary. But many contracts require you to keep records and to give notice of delay or change within set time limits, and a diary is the simplest way to show you did. Records made at the time carry far more weight than recollections written up later.

What to record every day

Keep it factual and quick. If it takes more than a couple of minutes, it will not get done on a busy day.

The entry that matters most is the one about a problem. Delays, changes and incidents are the entries people ask for later, so write those up on the day, with the cause and the effect, even when everything else gets a line.

An example entry

DateTuesday 14 October 2025, Heathfield Road
WeatherHeavy rain 07:00 to 11:30. Dry and overcast after.
On siteGroundworks: 4. Bricklayers: 2. Site manager.
Work doneBlockwork to plots 3 and 4 stopped at 08:00 because of rain. Restarted 12:00. Drainage trench to plot 5 excavated, not inspected.
Deliveries09:40: 480 concrete blocks, 6 rejected as damaged. Photos attached.
InstructionsClient's representative asked by phone at 14:15 to move the kitchen window 300 mm left on plot 3. No written instruction yet. Requested it by email at 14:30.
Delay4 hours lost to rain on blockwork, plots 3 and 4.
SafetyNo incidents. Toolbox talk on working near open trenches given at 07:45.

Note what it does: it gives times, names the cause of the lost hours, and records a verbal instruction together with the request to confirm it in writing. Those are the details people need later.

The mistakes that make a diary useless

How long to keep it

As a rule of thumb, a claim under a simple contract can be brought up to six years after the breach, and twelve years where the contract is a deed. Some claims have longer periods, so check with your solicitor or insurer before you destroy anything. Keep diaries at least that long and keep them where you can find them by site and date.

Paper or digital

Want a start? Use our free printable diary template.

A paper diary is fine if it is kept every day and kept safe. The trouble is that it is hard to search, easy to damage, tied to one person, and awkward to send to someone who needs it. A digital diary solves those, as long as it works without signal, is quick to fill in on a phone, and keeps a record of changes.

If you are not sure how your own set-up would hold up, our free 3-minute assessment asks a few questions about how you keep your diary, register and inductions and tells you where the gaps are.

Keep the diary on your phone, even with no signal

SiteHub lets you log the day with photos, weather, deliveries and voice notes on site. It syncs when you are back in signal, every entry is dated and searchable, and every site's diary can be exported as PDFs.

No card needed. £19 a month for your first site and £15 for each extra site after the trial.

This guide is general information for contractors, not legal advice. For a specific claim or dispute, speak to a solicitor or your insurer.